Construction Update May 13

  • 400

The construction team is hard at work with the following tasks:

• Timbers for the grand entrance and siding for the south building will be installed this week.
• The team is wrapping up electrical work in the lobby, and taping and dry wall installation will start early next week.
• Carpet went into the third floor on Tuesday, allowing furniture such as dressers and cabinets to be moved into those rooms.
• Bathroom tiles have also arrived and will be laid this week.
• Banquet chairs have been delivered, which are some of the first items to arrive for the hotel’s multi-room meeting and convention facility that will attract more events to the North Island.
• PHINNs remains closed for furniture assembly.

concrete-forming-update Construction crews form concrete on the pub side of Kwa’lilas Hotel.

cedar-siding-update k’awat’si Construction team enjoys sunny skies as they work to cut and finish the cedar siding for Kwa’lilas Hotel.
 
Carpet is installed and furniture is moved into the rooms on the 3rd floor of Kwa’lilas Hotel. Carpet is installed and furniture is moved into the rooms on the 3rd floor of Kwa’lilas Hotel.